Consol Energy Robinson Run Overland Conveyor

 
 
   

This NAFCO conveyor moves a ton and a quarter of material every hour.

The three Refuse Conveyor Belts dispose of refuse materials from the preparation plant to the disposal location six miles away over mountains, valleys, streams, and roads.

NAFCO is completing the manufacturing and shipping of the structural supports for CONSOL Energy in conjunction with the design/construction performed by Roberts & Schaefer Company.

NAFCO has shipped all of the 5,500,000 pounds of the conveyor support steel for the project.

 
     
       
    Capacity

24 hour 7 day a week service at a capacity of 2500 Tons per hour

 
    Construction Began in June 2005  
    In Service March 2007  
    Total Cost $25 Million